Sostanj lignite thermal power plant unit 6, Slovenia


a

NGOs such as Focus raised numerous issues with the Slovene government and international financial institutions but they showed no sign of taking concerns into account until the project was considered a fait accompli.

TEŠ6 now looks set to make losses of EUR 70-80 million annually (pdf) for the next few years at least.

Governments in other southeast European countries planning similar projects would do well to take note.

Quick facts
Loans from the European Investment Bank (EUR 550 million) and the European Bank for Reconstruction and Development (EUR 100 million) added up to more than 50% of the overall costs of the investment.

In 2013, a senior EIB source described TEŠ6 as “one of those projects that tends to haunt you”.


TEŠ6 promises higher efficiency, but not low-carbon energy

Initial concerns around TEŠ6 centred around its climate impact. Its promoters argued that the new unit would increase efficiency and reduce CO2 emissions, but forgot to mention that it would lock Slovenia into high-carbon electricity generation until beyond 2050.

Operating TEŠ6 will result in emissions of 3.4 mt CO2 per year, which is equivalent to almost all of Slovenia’s emissions in 2050 (if it cuts emissions by 80 percent – a minimum according to the European goals of 80-95 percent).

Doubling of initial costs

Since 2006, when the project was announced as part of a government investment wish-list, the the costs have more than doubled (pdf) from around EUR 600 million to EUR 1.43 billion.

The reasons for this are numerous but include alleged fraud of EUR 284 million that benefitted lead equipment supplier Alstom.

Alleged corruption


(A campaign cartoon portraying the former and directors of the Sostanj lignite power plant.)

In a report from February 2012, the Slovenian Commission for the Prevention of Corruption issued serious warnings that:

    "the project [TES 6] is designed and implemented in a non-transparent manner, lacks supervision and is burdened with political and lobbying influences, and as a result there has been [and still is] a high risk of corruption and conflict of interest".

After a lengthy investigation, in October 2014 ten people were charged with fraud in relation to the project.


Read more in our press releases:

The dirty French-Slovenian connection
February 23, 2012

EBRD freezes loan disbursements in Alstom's coal project over corruption allegations. NGOs call on the EIB to follow suit
April 18, 2012

Dubious economic assumptions

An analysis (pdf) carried out by consultants CE Delft in 2011 showed that the projected price of coal was unrealistic and that the project would be very sensitive to electricity prices.

Both of these issues have already turned out to be serious problems even before the plant goes into commercial operation: The sale price of electricity is currently lower than TEŠ6’s estimated cost of production and is expected to be for the next few years at least.

One of the assumptions behind the project and conditions for the state guarantee for the first EIB loan was that the price of lignite from Velenje mine does not exceed 2.25 EUR/GJ in 2015 or 2.73 EUR/GJ in 2054, and while the current sales price is being kept secret, the production price is around 2.9 EUR/KJ (pdf) so it is not likely that the assumptions behind the project are realistic.

Unrealistic claims about employment

One of the key arguments for construction of TEŠ6 was that it would enable long-term employment in the plant and nearby Velenje mine, and that the Šaleška Valley would otherwise face a social disaster.

However in October 2014, the management of TEŠ announced its plans to optimize the functioning of TEŠ: reorganization of the company would ensure that half – 226 of the current 452 – employees are laid off.

Lessons to be learnt

TEŠ6 is a good example of what can happen when a project is pushed forward to satisfy narrow interests without adequate transparency, public participation or an examination of alternatives. Had the project been opened up to scrutiny at an earlier stage, the mistaken assumptions behind the project could have been discussed and serious mistakes avoided.

It also vividly illustrates the fact that lignite can no longer be considered cheap and shows that ignoring economic warning signs early on will most likely backfire later on. This is a valuable lesson for countries in southeast Europe who are showing every sign of making similar mistakes with projects such as Pljevlja II and Tuzla 7.


For more information contact Pippa Gallop, Bankwatch's research co-ordinator

Share:

Latest developments


 

Press release | January 24, 2014

Ljubljana – The scandal-marred lignite plant TES 6 at Sostanj in Slovenia will likely cost 1.44 billion euros (2 billion US), more than double than what was initially predicted, and is due to produce annual losses of 50 million euros, show calculations recently revealed by Slovenian media. These cost escalations, predicted by NGOs critical of the project, should constitute a word of caution for other countries in South-Eastern Europe that are considering building new coal capacities.

Balkans, coal, EU, TES6
Press release | December 9, 2013

The European Bank for Reconstruction and Development has been approving financing for coal projects over which corruption allegations loom, and in some cases even while official corruption investigations were underway, according to an analysis published by CEE Bankwatch Network today.

Balkans
Blog entry | September 6, 2013

With another public action, colleagues in Moscow are today bringing to a close a week that has seen the European Bank for Reconstruction and Development having to listen to a lot of uncomfortable truths.

Blog entry | August 28, 2013

As part of the consultation on its energy sector strategy the EBRD next week hosts public meetings in Istanbul, Belgrade and Moscow to discuss with civil society from its countries of operation. While public pressure is increasing to end coal financing it is important to note that restrictions to carbon-intensive investments must be strictly and clearly defined in the strategy document if they are to improve the EBRD's climate impact. An article from Bankwatch's 2012 annual report (pdf) illustrates how a too flexible approach allows the EBRD to greenwash also very dirty investments.

Press release | July 22, 2013

London – The European Bank for Reconstruction and Development (EBRD) published July 19 a draft (pdf) of its future energy policy. According to CEE Bankwatch Network, although the bank correctly depicts the urgency of transitioning towards low-carbon economies, it falls short when it comes to commitments: lending to fossil fuels is envisaged to continue, including for coal, the dirties of fossil fuels; and promises to support renewables and energy efficiency, though welcome, are not accompanied by persuasive benchmarks and timelines.

Publications

Bankwatch Mail | May 10, 2013

If there is one sector in which the EBRD has been causing particular controversy in recent years, it is the energy sector. From lignite in Slovenia to hydropower in Georgia and nuclear in Ukraine, the bank has financed a series of projects that have incurred opposition from various quarters. Now that the EBRD is revising its Environmental and Social Policy it's time to take a look at what needs to be learned from these projects.

Bankwatch Mail | May 10, 2013

Following confirmation at the beginning of March that the European Investment Bank and the European Bank for Reconstruction and Development are paying out half a billion euros in loans for a new unit at the Sostanj lignite power plant (TES 6) in Slovenia, 98 organisations sent an open letter to both banks calling on them to never commit to such misguided loans again.

Briefing | April 22, 2013

With each passing day, there is less chance that we will manage to keep the planet within the "safe" limit of two degrees Celsius global warming that would avoid disastrous climate change. The European Investment Bank and the European Bank for Reconstruction and Development can play a pivotal role in leveraging more private investment for sustainable energy. Both institutions are now reviewing their energy lending policies.

Advocacy letter | March 20, 2013

After the EIB and the EBRD disbursed a promised 650 million euros for Slovenian lignite plant TES 6 on March 8, Focus Slovenia, CEE Bankwatch Network and 96 other NGOs sent this letter to the two banks calling on them to never commit to such a misguided loan again. The letter includes a list of reasons why Sostanj was undeserving of public loans and a set of measures that need to be taken by the banks immediately in order to avoid such mistakes from being repeated in the future.

Briefing | March 18, 2013

The Western Balkans countries are aspiring to become members of the European Union. At the same time, 6195 MW of new coal and lignite plants are planned to be built in the Western Balkans, which will still be operating by 2050 and threaten these countries' ability to comply with EU long-term decarbonisation objectives. The European Bank for Reconstruction and Development is planning to support some of these power plants via its loans.