Home >> Our Work >> Projects >> Kolubara B lignite-fired power plant, Serbia

Kolubara B lignite-fired power plant, Serbia


a

The Kolubara B thermal power plant site is situated near Kalenic village, 60 km south-west of Belgrade, at the northern side of the Tamnava Open Cast Mine. The decision to build the 2x350 MW plant was taken in 1983 and construction started in 1988. Construction progressed slowly until 1992, when work was suspended due to sanctions against Serbia. At this stage about 40 percent of the facility had already been constructed, partly with the assistance of a World Bank loan.

In 2011 the results of an international tender were announced, in which Italian utility Edison was the only company to submit a bid. Edison's offer was accepted, and a joint venture agreement signed with Elektroprivreda Srbija on the development of the Kolubara B project in June 2011.

The fact that some of the facility had already been constructed meant that technical questions arose relating to whether the plant could meet the latest EU standards. For example the agreement stated that the plant would have a net efficiency of 37 percent, but the EU's Best Available Techniques Reference Document stipulates that new lignite-fired plants using pulverised lignite technology should have an efficiency level of minimum 42-45%. The emissions limit values in the 2012 environmental impact assessment were not in line with the EU Industrial Emissions Directive.

In the meantime in July 2011 the European Bank for Reconstruction and Development (EBRD) approved an EUR 80 million loan to provide new equipment for the Kolubara lignite mines. (For more information about the project see here).

Although in March 2012 the EBRD announced that it was considering investing in the Kolubara B plant, on 6 September 2013, it confirmed to Bankwatch by e-mail that it was no longer examining participation in the Kolubara B project [1] after a full year of corruption cases related to the Kolubara complex and complaints to the Bank’s Project Complaint Mechanism.

This announcement was shortly followed by the news on 9 September 2013 that early that day the police had arrested former director of the Kolubara Mining Basin Nebojsa Ceran and former financial director Ljubisa Nekic, businessman Radoslav Savatijevic, and several other individuals. The arrestees are suspected of fraud in land expropriation proceedings around the Kolubara mine.

An additional risk to this project is the fact that the Environmental Impact Assessment (EIA) study for Kolubara B expired in July 2014. This is caused by inactivity of investors. The legal provisions envisage concrete activities on the investors’ side or permitting activities in time frame of two years. None of these took place, therefore the study now expired.

Given these risks, investments in Kolubara at the present time should be approached with caution. However in the future, provided that the integrity and environmental legacy issues in the company are adequately addressed, we believe there are rich opportunities for renewable energy projects such as solar or sustainable biomass production on rehabilitated land at the site. Some reforestation projects have been undertaken on some parts of the site, but the majority remains open for rehabilitation.

Notes

1. The relevant section reads:

“Please let me confirm that we have not been working actively on this project in the last two years. We have also informed the client that, should the project become active again, it will have to be assessed against the new energy strategy which has far more stringent rules and would make our possible participation very difficult.”

Share:

Latest developments


 

Blog entry | September 7, 2015

By now regular readers of the Bankwatch blog will know that the energy system in southeast Europe is corrupt, dirty and inefficient. But we now have an opportunity to change it.

Press release | June 8, 2015

Prague - New investments in coal mines and power plants could cost the Western Balkans and Ukraine dearly if they fail to take into account binding rules on subsidies (State aid), according to a new briefing released today by CEE Bankwatch Network.

Blog entry | March 23, 2015

Western Balkan countries have ambitious plans to increase their electricity generation over the next years. But what will happen if they all become a regional energy hub? Will there be a demand for all the available electricity?

Press release | March 19, 2015

The Western Balkans countries have strong electricity export ambitions that create the danger of stranded assets, finds a new report launched by CEE Bankwatch Network today. If governments take electricity expansion decisions without taking due account of developments in other countries, the region will have to compete with other nearby exporters and may find that its power plants become uneconomic.

Blog entry | March 19, 2015

Today we've published a new report analysing future energy trends in countries of the western Balkans.

From a robust dataset we researched together with the University of Groningen and the consultancy 'The Advisory House', we've pulled out a couple of illustrations.

Publications

Study | June 8, 2015

By signing the Energy Community Treaty in 2005, countries in the Western Balkans, Ukraine and Moldova agreed that the European Union's competition rules are to be applied also within their territory. A number of energy sector investments are being planned that may not so far have taken adequate account of State aid rules. This briefing therefore provides a summary to draw attention to relevant requirements of EU law and highlight the risks of failure to take them into account when planning investments. The account when planning investments.

Bankwatch Mail | May 14, 2015

Western Balkan countries have ambitious plans to increase their electricity generation over the next years. But what will happen if they all become a regional energy hub? Will there be a demand for all the available electricity?

Bankwatch Mail | May 14, 2015

Earlier this year, Serbian media reported that the EBRD was considering providing a new EUR 200 million loan for the financial restructuring of the state-owned electric utility power company of Serbia, EPS. The EBRD Director for Serbia, Mateo Patrone, was quoted by B92.net saying that the loan is aimed at helping the financial restructuring of EPS. Meanwhile, the EBRD's country strategy for Serbia, approved by its board of directors last April, highlights the bank's “key role in promoting energy efficiency and renewable energy” for the country.

Study | March 19, 2015

Country chapters available for Albania, Bosnia and Herzegovina, Kosovo, Macedonia, Montenegro, Serbia.

For other languages, see here.

Analysing the estimated energy demand and production capacities in Western Balkan countries, this study shows that if countries realise their planned capacity expansions, the region will have a 56 per cent electricity surplus in 2024, led by Bosnia and Herzegovina and Serbia. Nearly all governments in the region aspire to become electricity exporters, but the study argues that if governments fail to take into account the regional perspective, they could end up with power plants becoming simply uneconomic to operate.