Home >> Our Work >> Projects >> Southern Gas Corridor / Euro-Caspian Mega Pipeline

Southern Gas Corridor / Euro-Caspian Mega Pipeline


a

Key points

  • Project is slated to receive unprecedented support from public finance institutions. more >>

  • Study reveals a worrying track record of criminal and corrupt activities among companies building the pipeline. more >>

  • Project would widen surplus in Europe’s gas import infrastructure and likely turn into stranded asset. more >>

  • Constructions are having large, unjust impacts on local communities in transit countries. more >>

  • Gas to come from Azerbaijan, but deal will strengthen repressive Aliyev regime. Human rights defenders to take the brunt. more >>

  • Web documentary shows project not needed, highlights opposition and alternatives to pipeline. more >>

 

Record loans from public banks



Click for more details >>

 

Key facts


Costs: estimated at USD 45 billion
Length: 3500 km
Capacity: 16 billion cbm of gas annually

Pipelines

  • South Caucasus Pipeline extension (SCPx): Azerbaijan-Georgia
  • Trans-Anatolian Pipeline (TANAP): Turkey
  • Trans-Adriatic Pipeline (TAP): Greece-Albania-Italy

Gas supply

  • Azerbaijan: Shah Deniz gas field, located in the Caspian Sea
  • Turkmenistan: maybe at a later stage
  • Iran: has been mentioned

See a breakdown of approved and proposed public finance for the Southern Gas Corridor (Google sheet)

The European Bank for Reconstruction and Development (EBRD) already approved two loans for the Shah Deniz stage 2 gas field (USD 200 million and USD 250 million, the latter as part of a larger package, (see below)) and is considering a third to the tune of USD 100 million. It is currently also reviewing the concept for a loan for TANAP (size as yet unclear) while having stated that it considers USD 1 billion for TAP and TANAP together.

On top of USD 250 million for Shah Deniz stage II (as part of a USD 1 billion financing package with the EBRD and commercial banks), the Asian Development Bank (ADB) approved in December 2016 an additional USD 1 billion for the Shah Deniz II gas field.

The European Investment Bank (EIB) considers EUR 2 billion for TAP and EUR 1 billion for TANAP.

The World Bank approved two USD 400 million loans for Turkey and Azerbaijan for TANAP. The World Bank's Multilateral Investment Guarantee Agency (MIGA) approved a guarantee of up to USD 950 million for TANAP against the risk of non-honoring of a sovereign financial obligation.

The Asian Infrastructure Investment Bank (AIIB) approved a USD 600 million loan for TANAP (pdf) at an unannounced extra-ordinary virtual Board meeting on December 21. (The AIIB's project summary also states the combined EIB and EBRD support for TANAP as USD 2.1 billion, which suggests that, like the EIB, the EBRD is considering EUR 1 billion for TANAP.)

 

Earlier, already completed loans from the EBRD include support for the Southern Caucasus gas pipeline (SCP) (USD 70 million for Lukoil (2005) and USD 60 million for SOCAR (2004)) and the Shah Deniz gas field (USD 110 million for Lukoil (2005) and USD 100 million for SOCAR (2004)).

Both Shah Deniz and the South Caucasus Pipeline are considered parts of the Southern Gas Corridor's infrastructure as the EBRD's Managing Director for Energy and Natural Resources, Riccardo Puliti has stated.

 

Backing from Brussels

The pipeline is a key element of the Energy Union, the European Commission's flagship initiative. TAP could also benefit from financing through the Project Bond Initiative as a Project of Common Interest.

 

A predictable stranded asset


Massive new gas infrastructure like this will lock Europe into fossil fuels for decades and will lead to hundreds of millions of tonnes of CO2 emissions.

The EU already has an overall surplus of gas import infrastructure. Especially since the 2007 recession, gas demand has significantly decreased (pdf) and is not expected to bounce back until the 2020’s.

The European Union’s 2050 Energy Strategy expects natural gas imports to further decrease under all scenarios. The 2020’s, when the pipeline is expected to be operational, should already mark a significant reduction in gas demand according to this roadmap.

The Southern Gas Corridor would only widen the surplus in Europe’s gas import infrastructure and likely turn into a liability.

>> Read more:
Pipe dreams - why public subsidies for Lukoil in Azerbaijan will not reduce EU dependency on Russia
Study | January 21, 2015

No security for Europe from the Southern Gas Corridor
Blog post | May 15, 2016
 

 

Gas firms lobbied to weaken EU renewables target


Bringing more gas to Europe would be at odds with the EU's climate leadership aspirations, its emission reduction goals (40% cut by 2030) and its renewables targets (27% in 2030).

This dissonance between the EU's goals and planned investments is no coincidence. Big energy corporations have a great deal to lose if we shift away from a centralised energy system that depends on fossil fuels.

Gas companies like BP, one of the main companies involved in the Southern Gas Corridor, have lobbied intensively against renewables subsisides and for a greater role for gas in the EU's energy plans.

>> Read more:
BP lobbied against EU support for clean energy to favour gas, documents reveal
guardian.co.uk | August 20, 2015

Walking the line, Chapter 4.1 Big energy
Web documentary | March 8, 2016

 

Risky business - Who benefits from the Southern Gas Corridor?


No less than 15 firms contracted to build TAP and TANAP, the two main sections of the Southern Gas Corridor, have been implicated in various forms of corruption in the past.

All the details and an interactive presentation are at https://bankwatch.org/risky-business

Image with text: 15 dodgy companies, 2 pipelines, billions in European public money'

 

Web documentary


Experience a walk along the pipeline and imagine the devastating consequences for people and the environment from Azerbaijan to Italy if the project is built. Watch the web doc >>

Watch the web doc

 

Impacts and opposition in transit countries


Italy


The section of the beach where TAP would hit shore. (Click to see larger image. Source for location: TAP official website.)

The TAP pipeline is supposed to reach land in San Foca in the Melendugno municipality. San Foca has received European Blue Flags for not one but two beaches, awarding water quality and environmental management among others.

Fearing the destruction of their coastline and negative effects on tourism, agriculture and fishery, local mayors and their constituencies are viciously opposing the TAP pipeline and the risks of accidents associated with the related infrastructure.

Read more:
Italian communities block pipeline works to save ancient olive trees

 

Albania & Greece

Land acquisition for the pipeline and the compensation of local farmers has led to a number of grievances and irregularities in both Greece and Albania. Some farmers have lost the majority of their income while receiving a pittance in return.

Read more:
Last harvest looming for Albanian farmers along pipeline route
Multimedia story | December 7, 2016

'We have no other option' - Preparation of the Trans-Adriatic Pipeline in Albania (pdf)
Study | August 4, 2016

When Athens can’t tell a Trojan horse
Multimedia story | December 2, 2016

 

“I was arrested and tortured for speaking out against the BTC pipeline. If the [Southern Gas Corridor] goes ahead, people living along it will experience the same repression.”

Ferhat Kaya, Turkish activist in the Ardahan province (Source: Platform)

Turkey

The Trans Anatolian Pipeline (TANAP) pipeline will pass through twenty provinces in Turkey. It will create a high security, militarised corridor across the whole country, with costs estimated at USD 11.7 billion.

Although Turkish officials claim that the pipeline will result in higher employment, lessons from the BTC pipeline indicate that locals may rather face loss of land and livelihoods, environmental problems and repression if they dare to protest.

 

Strengthening the dictatorship in Azerbaijan


In Azerbaijan the Aliyev family’s dictatorship has held onto power for the past two decades through a combination of holding fraudulent elections, prosecuting and assaulting critics and curtailing media freedom.

During the October 2013 presidential elections almost 150 political prisoners were behind bars in Azerbaijan. The OSCE criticised the elections for failing to meet international standards on free and fair elections.

Since summer 2014, ahead of the inaugural European Games in Azerbaijan, unprecedented levels of arrests and attacks on civil society, even by Azerbaijan’s standards, have occurred. By 2015 several renowned human rights defenders have been sentenced to years in prison. The OSCE was ordered by Azerbaijan to close their mission in the country. Critical voices, including the guardian and amnesty international, were banned from covering the European Games in Baku.

The EBRD’s founding mandate states that it must only work in countries that are committed to democratic principles. Azerbaijan is proving itself to be the opposite.

Read more in a letter by the Sports for Rights campaign to the EBRD


Khadija Ismayilova, an outspoken critic of the Aliyev regime, has been blackmailed, threatened and arrested.

 

Azerbaijan downgraded in Extractive Industries Transparency Initiative

The Board of the Extractive Industries Transparency Initiative (EITI), a coalition of companies, governments, investors and civil society organisations has unanimously downgraded Azerbaijan to a "candidate country". Azerbaijan will be suspended from the EITI in April 2016 if it does not comply with a set of requirements that ensure civil society can work freely in the country.

By approving a loan for the Shah Deniz gas field, the EBRD is in fundamental conflict with its own policies that explicitly commit the bank to the EITI process. The EBRD’s Energy Policy states that “[t]he Bank is committed to adhere to best governance, transparency and revenue management standards by requiring its clients to implement the principles and requirements of the EITI.”

>> Read more
Publish What You Pay: 'Lukoil loan would fundamentally contradict EBRD policies' (pdf)
Advocacy letter | July 21, 2015

 

Oil, gas, money, power

"[O]il has kept autocrats in power by enabling them to increase spending, reduce taxes, buy the loyalty of the armed forces, and conceal their own corruption and incompetence..."

Micheal L. Ross, 'The Oil Curse: How Petroleum Wealth Shapes the Development of Nations', 2012

Without properly functioning democratic institutions, rule of law and effective checks and balances for the president's powers, investments in Azerbaijan's oil and gas sector will further cripple democracy in the country.

Hydrocarbon revenues provide the Aliyevs with the finance needed to pay security forces and establish a secure income and therefore enabled them to ignore citizens’ voices because they are not reliant on those citizens for a tax base.

Human rights activist Rasul Jafarov spoke about this shortly before his arrest. Referring to an earlier mega pipeline project that has equally been criticised, he said:

“Before the oil and gas incomes came to Azerbaijan we had more democracy and freedom. The main income from oil came in 2005 when the Baku-Tbilisi-Ceyhan pipeline started to operate. And from that time the situation started to deteriorate.”

 

>> Read more:
Europe's Caspian gas dreams - a nightmare come true for human rights in Azerbaijan
Blog post | May 15, 2015

Sport for Rights to EBRD: No public money for Lukoil and mega gas project in Azerbaijan
Advocacy letter | July 20, 2015

 

 

The BTC pipeline - will history repeat itself?

The Baku-Tbilisi-Ceyhan (BTC) oil pipeline project, financed by the EBRD and other public lenders, was touted as a world class model development project and BP, the project sponsor, agreed to standards set by the OECD and the US and UK government’s principles on human rights (pdf).

Yet criticising the BTC pipeline was not tolerated in the three countries involved - Azerbaijan, Georgia and Turkey. While journalists were arrested in Azerbaijan, critics were intimidated, arrested and even tortured in Turkey.

In 2011, the UK government announced that the BTC Company had broken the commitments it had made to international human rights standards. Already in 2010, following a complaint to the U.S. government, the Overseas Private Investment Corporation, another project investor, recommended (pdf) that BP needed more precautions to safeguard the pipeline and “to comply with the applicable environmental and social policies and guidelines of the lenders [...] and with national law.”

>> READ ALSO:
The Oil Road - How a done deal continues to unravel
Bankwatch Mail article | October 8, 2012

 

See an overview of the shareholders of Shah Deniz and the three pipelines in this spreadsheet >>

 

Background: Shareholder companies


BP

With total revenues of USD 358.7 billion for 2014 alone, British Petroleum (BP) is one of the world’s largest oil and gas companies. Yet, it is also renown for Deepwater Horizon, the largest marine oil spill in history.

SOCAR

The State Oil Company of Azerbaijan (revenues in 2014: USD 39.7 billion) is one of the strongest Azeri institutions holding the Aliyev dictatorship in place. SOCAR uses its own paramilitary force to silence journalists. It is known for a general lack of transparency and links to the Aliyev dictatorship.

Lukoil

Lukoil is the second largest Russian oil and gas company (revenues in 2013: USD 141.5 billion). Apart from the problem of entrusting a Russian company to diversify the EU away from Russian gas, Lukoil is responsible for numerous oil spills and accidents in Russia, while receiving money from the EBRD.

See an overview of the shareholders of Shah Deniz and the three pipelines in this spreadsheet >>

 

 

Share:

Latest developments


 

Press release | May 8, 2017

In a last minute attempt to force facts on the ground, the Italian authorities have enabled the removal of a group of olive trees to make room for a future construction site of the Trans-Adriatic Pipeline (TAP), despite an earlier agreement between the company and local institutions. Nevertheless, the company has not been able to clear the site by the official deadline and the residents have vowed to step up their protest against the largest energy project the EU is currently pursuing.

Blog entry | April 12, 2017

This article first appeared on the Re:Common website.


It was the end of February and the scene is Baku, the capital of Azerbaijan. During an official meeting, the Italian government was severely criticised for the considerable delays in the construction of the Trans Adriatic Pipeline (TAP), part of the Southern Gas Corridor.

Blog entry | March 23, 2017

An ancient olive grove in southern Italy is currently on the frontlines of grassroots resistance to the Southern Gas Corridor project, the EU’s flagship energy project.

Press release | March 10, 2017

A decision to suspend Azerbaijan’s membership in the Extractive Industries Transparency Initiative (EITI) adopted yesterday (Mar 9) is the latest reminder for international financial institutes to avoid supporting the Southern Gas Corridor (SGC) project.

Blog entry | March 7, 2017

It is fitting that we use today to reflect on the European Investment Bank’s new Strategy on Gender Equality and Women's Economic Empowerment: 8 March is International Women’s Day. Adopted at the beginning of this year, the strategy complements the bank’s existing social policy and reflects the equality principle of the EU Charter of Fundamental Rights.

Publications

Advocacy letter | December 19, 2016

A group of 39 international NGOs sent a letter to the Directors of the World Bank (WB) today urging the Bank not to finance the Trans Anatolian Pipeline (TANAP). TANAP is the Eastern part of the Southern Gas Corridor, a 3500 kilometres-long chain of gas pipelines from Azerbaijan to Europe.

The WB Directors will consider on December 20th a loan to the Turkish company Botas for the construction of the pipeline.

Study | December 13, 2016

The Southern Gas Corridor, a string of pipelines meant to bring gas from Azerbaijan into Europe, is presented as a panacea for all ills and is set to benefit from some of the biggest loans in the history of European public banks. But as this report reveals, Europe's flagship energy project is set to benefit a host of companies and individuals with a particularly shady track record. Several companies contracted to build the Southern Gas Corridor have a worrying history of corruption.

Advocacy letter | December 5, 2016

Ahead of the Asian Development Bank's board meeting where a loan to the Shah Deniz gas expansion project in Azerbaijan is to be discussed, a group of NGOs ask the ADB board to postpone a decision and align the ADB to the practice of other IFIs involved in financing the same and related gas projects.

Advocacy letter | December 5, 2016

Ahead of an expected loan decision by the Asian Development Bank for the Shah Deniz gas field in Azerbaijan, non-governmental organisations raised concerns over the human rights situation in the country as well as in Turkey, to where the gas from Shah Deniz will be transported via the Southern Gas Corridor.

Advocacy letter | November 29, 2016

In this letter, Human Rights Watch and Bankwatch highlight the ongoing repression of independent civil society in Azerbaijan and its impact on sustainable develpoment and urge the European Bank for Reconstruction and Development to limit its engagement in the country, specifically to not provide financing for projects related to the country's extractives sector such as the Trans-Anatolian Gas Pipeline (TANAP) and the Trans-Adriatic Pipeline (TAP).